KE’s $450mn project in full swing at Surjani

0
39

By Shakil Paracha

KARACHI: Development work is currently underway in areas of North Karachi and Surjani Town where two 220 kV towers have been erected for expansion of transmission network in the area. The two pylons will connect the transmission lines to the new 220 KV grid station being developed in Surjani. This new Grid Station is expected to commence operations by end of December 2018 and is part of a $450million transmission enhancement project aimed to enhance reliability of electricity to the area. Upgradation work is also being carried out at the existing grid station serving the Surjani area.